schedule:
|
|
- name: mitaka
|
|
length: 24
|
|
release-week: 2016-04-04
|
|
|
|
events:
|
|
R-18:
|
|
- mitaka-1: >
|
|
Dec 1-3 is the mitaka-1 milestone window for projects following the
|
|
release:cycle-with-milestones model.
|
|
R-11:
|
|
- mitaka-2: >
|
|
Jan 19-21 is the mitaka-2 milestone window for projects following
|
|
the release:cycle-with-milestones model.
|
|
R-5:
|
|
- mitaka-3: >
|
|
Libraries that are not client libraries (Oslo and others) should
|
|
issue their final release during this week. That allows to give
|
|
time for last-minute changes before feature freeze.
|
|
- Feature freeze: >
|
|
The mitaka-3 milestone marks feature freeze for projects following
|
|
the release:cycle-with-milestones model. No featureful patch should
|
|
be landed after this point. Exceptions may be granted by the
|
|
project PTL.
|
|
- Final release for client libraries: >
|
|
Client libraries should issue their final release during this week,
|
|
to match feature freeze.
|
|
- Soft StringFreeze: >
|
|
You are no longer allowed to accept proposed changes containing
|
|
modifications in user-facing strings. Such changes should be
|
|
rejected by the review team and postponed until the next series
|
|
development opens (which should happen when RC1 is published).
|
|
R-3:
|
|
- RC1 target week: >
|
|
The week of March 14-18 is the target date for projects following
|
|
the release:cycle-with-milestones model to issue their first
|
|
release candidate.
|
|
- Hard StringFreeze: >
|
|
This happens when the RC1 for the project is tagged. At this point,
|
|
ideally no strings are changed (or added, or removed), to give
|
|
translator time to finish up their efforts.
|
|
R-1:
|
|
- Final RCs and intermediary releases: >
|
|
The week of March 28 to April 1st is the last week to issue release
|
|
candidates or intermediary releases before release week. On release
|
|
week only final-release-critical releases will be accepted (at the
|
|
discretion of the release team).
|
|
R-0:
|
|
- Mitaka release: >
|
|
The Mitaka coordinated release will happen on April 7th.
|
|
|
|
- name: newton
|
|
length: 25
|
|
release-week: 2016-10-03
|
|
|
|
events:
|
|
R-23:
|
|
- Newton Design Summit: >
|
|
R-18:
|
|
- newton-1 milestone: >
|
|
May 31 - June 2 is the newton-1 milestone window for projects
|
|
following the release:cycle-with-milestones model.
|
|
R-12:
|
|
- newton-2 milestone: >
|
|
July 12-14 is the newton-2 milestone window for projects following
|
|
the release:cycle-with-milestones model.
|
|
R-6:
|
|
- Final release for non-client libraries: >
|
|
Libraries that are not client libraries (Oslo and others) should
|
|
issue their final release during this week. That allows to give
|
|
time for last-minute changes before feature freeze.
|
|
R-5:
|
|
- newton-3 milestone: >
|
|
August 30 - Sept 1 is the newton-3 milestone window for projects
|
|
following the release:cycle-with-milestones model.
|
|
- Feature freeze: >
|
|
The newton-3 milestone marks feature freeze for projects following
|
|
the release:cycle-with-milestones model. No featureful patch should
|
|
be landed after this point. Exceptions may be granted by the
|
|
project PTL.
|
|
- Final release for client libraries: >
|
|
Client libraries should issue their final release during this week,
|
|
to match feature freeze.
|
|
- Soft StringFreeze: >
|
|
You are no longer allowed to accept proposed changes containing
|
|
modifications in user-facing strings. Such changes should be
|
|
rejected by the review team and postponed until the next series
|
|
development opens (which should happen when RC1 is published).
|
|
- Requirements freeze: >
|
|
After the newton-3 milestone, only critical requirements and
|
|
constraints changes will be allowed. Freezing our requirements list
|
|
gives packagers downstream an opportunity to catch up and prepare
|
|
packages for everything necessary for distributions of the upcoming
|
|
release. The requirements remain frozen until the stable branches
|
|
are created, with the release candidates.
|
|
R-3:
|
|
- RC1 target week: >
|
|
The week of September 12 is the target date for projects following
|
|
the release:cycle-with-milestones model to issue their first
|
|
release candidate.
|
|
- Hard StringFreeze: >
|
|
This happens when the RC1 for the project is tagged. At this point,
|
|
ideally no strings are changed (or added, or removed), to give
|
|
translator time to finish up their efforts.
|
|
R-1:
|
|
- Final RCs and intermediary releases: >
|
|
The week of September 26 is the last week to issue release
|
|
candidates or intermediary releases before release week. On release
|
|
week only final-release-critical releases will be accepted (at the
|
|
discretion of the release team).
|
|
R-0:
|
|
- Newton release: >
|
|
The Newton coordinated release will happen on October 6th, 2016.
|