Merge "Fix erroneous dates in schedule details"
This commit is contained in:
commit
eeed7173c4
|
@ -36,7 +36,7 @@ release schedule.
|
||||||
Dalmatian-1 milestone
|
Dalmatian-1 milestone
|
||||||
---------------------
|
---------------------
|
||||||
|
|
||||||
30 May, 2024 is the Dalmatian-1 milestone. See project-specific notes
|
May 16, 2024 is the Dalmatian-1 milestone. See project-specific notes
|
||||||
for relevant deadlines.
|
for relevant deadlines.
|
||||||
|
|
||||||
.. _d-cycle-trail:
|
.. _d-cycle-trail:
|
||||||
|
@ -45,14 +45,14 @@ for relevant deadlines.
|
||||||
----------------------------------------------
|
----------------------------------------------
|
||||||
|
|
||||||
All projects following the cycle-trailing release model must release
|
All projects following the cycle-trailing release model must release
|
||||||
their 2024.1 Caracal deliverables by 13 June, 2024.
|
their 2024.1 Caracal deliverables by June 6, 2024.
|
||||||
|
|
||||||
.. _d-2:
|
.. _d-2:
|
||||||
|
|
||||||
Dalmatian-2 milestone
|
Dalmatian-2 milestone
|
||||||
---------------------
|
---------------------
|
||||||
|
|
||||||
18 July, 2024 is the Dalmatian-2 milestone. See project-specific notes
|
July 4, 2024 is the Dalmatian-2 milestone. See project-specific notes
|
||||||
for relevant deadlines.
|
for relevant deadlines.
|
||||||
|
|
||||||
.. _d-mf:
|
.. _d-mf:
|
||||||
|
@ -94,7 +94,7 @@ changes before feature freeze.
|
||||||
Dalmatian-3 milestone
|
Dalmatian-3 milestone
|
||||||
---------------------
|
---------------------
|
||||||
|
|
||||||
29 August, 2024 is the Dalmatian-3 milestone. See project-specific notes
|
August 29, 2024 is the Dalmatian-3 milestone. See project-specific notes
|
||||||
for relevant deadlines.
|
for relevant deadlines.
|
||||||
|
|
||||||
.. _d-ff:
|
.. _d-ff:
|
||||||
|
@ -142,7 +142,7 @@ frozen until the stable branches are created, with the release candidates.
|
||||||
RC1 target week
|
RC1 target week
|
||||||
---------------
|
---------------
|
||||||
|
|
||||||
The week of 9 September, 2024 is the target date for projects following the
|
The week of September 9, 2024 is the target date for projects following the
|
||||||
`release:cycle-with-rc`_ model to issue their first release candidate.
|
`release:cycle-with-rc`_ model to issue their first release candidate.
|
||||||
|
|
||||||
.. _d-hard-sf:
|
.. _d-hard-sf:
|
||||||
|
@ -159,7 +159,7 @@ finish up their efforts.
|
||||||
Final RCs and intermediary releases
|
Final RCs and intermediary releases
|
||||||
-----------------------------------
|
-----------------------------------
|
||||||
|
|
||||||
The week of 23 September, 2024 is the last week to issue release
|
The week of September 23, 2024 is the last week to issue release
|
||||||
candidates or intermediary releases before release week. During release week,
|
candidates or intermediary releases before release week. During release week,
|
||||||
only final-release-critical releases will be accepted (at the discretion of
|
only final-release-critical releases will be accepted (at the discretion of
|
||||||
the release team).
|
the release team).
|
||||||
|
@ -169,7 +169,7 @@ the release team).
|
||||||
Dalmatian release
|
Dalmatian release
|
||||||
-----------------
|
-----------------
|
||||||
|
|
||||||
The Dalmatian coordinated release will happen on Wednesday, 2 October, 2024.
|
The Dalmatian coordinated release will happen on Wednesday, October 2, 2024.
|
||||||
|
|
||||||
.. _d-cycle-highlights:
|